Construction of HVAC System for the Main Stadium of Al Sadd Club «Back

Project Description:

 

The project consists of a plant room with three cooling towers (1,069 m²) that provide a new air-conditioning system to the stadium's opening space by two separate air plenums; one around the playground area and another one under the spectators' seats.

 

The project entailed the following:

•  Water proofing works at roof top of plant room.

•  Earthing works.

•  Epoxy-painted floor in chiller room.

•  GRP (Glass Fiber Reinforced Plastic) ceiling works at west & south side.

•  Reinstallation of Lighting fixtures, fire alarm & grills at west & south side, indoor.

•  Dry Wall at east, north and south.

•  Restoration of external pavement tiles.

•Installation of diffusers support at west side.

 

Contract Value: QAR 81,643,366

 

Construction Challenges:

 

•  Lack of supply of GRP materials and ceiling accessories which are supplied by the Client from Dubai.
•  Stoppage of the works at the site due to scheduled games during the construction process at Al-Sadd Stadium.